Error:
Production order #### could not be scheduled.
No resource/resource group could be found that meets the requirements
Solution:
Go to Organization administration >> Common >> Resources
>> Resources capabilities
Click add and create a new resource and add it to the particular
Resource capabilities, Then if you want you can set the effective period all
for that particular resource.
Go to Resource ID then select the Resource groups, there you
choose based on the input warehouse.
Now you can complete the Production transactions.
You can learn more about AX in below links..!
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/not-enough-capacity-error-resolution
ReplyDeleteI had the same issue, the solution is to check the warehouse on the resource group , should be the same as production order warehouse https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/not-enough-capacity-error-resolution